LIVERPOOL, NEW YORK

PROJECT UPDATE

Click figure above for larger view

In 2014, Lockheed Martin began cleanup activities in the most upstream portion of the Bloody Brook remediation site (the wooded area near the NYS Thruway).  

  • Approximately 624 truckloads (approximately 13,000 tons or 9,000 cubic yards) of soil and brook sediment were removed from this area in 2014.
  • All of the wooded areas were restored with grass, shrubs and trees as well as three new wetland/pond areas that were made to create new brook capacity for flood control during high flow conditions as well as enhancing habitat for local wildlife.
  • See the August, October and December 2014 editions of the “Bloody Brook Voluntary Cleanup Newsletter" for photos and more information.

       View upstream of Lockheed from Wooded Area - Aug 2016                                                                                  Click on Photo 1 for larger view

The 2015 cleanup effort began in April in the wooded area where the 2014 activities left off, and continued downstream through the residential area up to the Floradale Road brook crossing.  

  • Approximately 870 truckloads (approximately 21,000 tons or 14,000 cubic yards) of upland and side bank soil and brook sediment was removed. 
  • The gabion baskets (metal caging filled with rocks) that lined the brook banks between the Midwood Drive access area and Brookview Lane were also removed and restored with a more natural, gentle slope and with vegetation as well as stone.
  • All disturbed areas were restored with grass, shrubs and trees.  In addition, any fences or sheds disturbed on residential properties were replaced.
  • The aging, corrugated metal culverts which move the brook underneath Brookview Lane, Sunflower Drive and Floradale Road were replaced with concrete box culverts which also included new pavement and guardrails.  
  • See the June, August and October 2015 editions of the “Bloody Brook Voluntary Cleanup Newsletter” for photos and more information.

View Downstream of Former Gabion Baskets from Midwood Drive Access Area to Brookview Lane – August 2016

                    Click on Photo 2 for larger view

View From Sunflower Drive Downstream to New Floradale Road Culvert – August 2016

Click on Photo 3 for larger view

In 2016, remedial construction activities resumed in May beginning at the downstream side of the Floradale Road brook crossing. 

  • Contractors have removed approximately 120 truckloads (2,900 tons or 1,900 cubic yards) of soil and sediment from the site through July 2016. 
  • The corrugated metal culverts underneath Pearl Street and Town Garden Drive were repaired and lined with concrete.
  •  Monitoring and watering of restored upstream areas has been necessary due to the lack of rain this summer.

Upcoming activities include:

Town Garden Drive Culverts: Before and After Remediation and Repair - August 2016

Click on Photo 4 for larger view

  Look for more information as the project continues in 2016 in the “Bloody Brook Voluntary Cleanup Newsletters” posted on this website as well as outside the access points to the Bloody Brook remediation site.







HISTORICAL TIMELINE OF INVESTIGATON & CLEANUP

1947 - General Electric (a Lockheed Martin heritage company) opened its doors at Electronics Park.

1993 - The facility became part of Martin Marietta in 1993.

1995 - The facility became part of Lockheed Martin after Martin Marietta and Lockheed merged.

1996 - The New York State Department of Environmental Conservation (NYSDEC), during an environmental investigation of tributaries that flow into Onondaga Lake, detected elevated cadmium levels.  

1996 - Following NYSDEC testing, Lockheed Martin began voluntary environmental investigations.

1997 - Lockheed Martin removed 325 tons of sediment from a 750-foot stretch of the West Branch of the brook closest to the facility.

2001-2007 - Lockheed Martin collected more than 1,000 soil samples further downstream and found elevated levels of cadmium at depths ranging to 15 feet 

2002 - Lockheed Martin entered into a Voluntary Cleanup Agreement with NYSDEC.

2005 - Lockheed Martin created a Remedial Action Work Plan (RAWP) that it submitted to NYSDEC

2008 - Lockheed Martin removed sediment from four sets of culverts along the West Branch of Bloody Brook.

2009 - Lockheed Martin assisted with soil removal from properties included in an Onondaga County stormwater drainage improvement project.

2009 - Lockheed Martin submitted a revised RAWP  

2010-2011 - Lockheed Martin and NYSDEC determined that additional soil samples needed to be collected from properties  

2011 - Lockheed Martin submitted a sampling work plan to the NYSDEC which was approved

2013 - Lockheed Martin submitted a revised RAWP to NYSDEC which incorporated the results of the 2011 soil sampling.

2013 - Lockheed Martin collected additional soil samples from some residential properties.

2013 - NYSDEC completed its review of the 2013 revision to the RAWP, and based on its content, developed a Proposed Decision Document

2014 - Tree Removal Work Plan for  2015 Construction Season was released

2014  - NYSDEC issued a final Decision Document which included responses to public comments and the administrative record for the site

2015 - Construction & Restoration Work Plan was released

2016 - Construction & Restoration Work Plan was released

2016 - Tree Removal Work Plan & Waste Characterization Soil Sampling Plan was released


GLOSSARY: View a list of terms commonly used in relation to general environmental remediation efforts that can be found throughout this Web site.

 

ACRONYMS: View a list of nicknames commonly used in relation to general environmental remediation efforts that can be found throughout this Web site.

 



 

If you have questions, please don’t hesitate to contact:

JILL FONTE,  PROJECT MANAGER JILL.A.FONTE@LMCO.COM

OR

Mékell Mikell,                         Corporate Communications
301-897-6934  Mekell.T.Mikell@lmco.com