LIVERPOOL, NEW YORK

Site Map

ABOVE: SITE MAP - CLICK ON MAP FOR LARGER VIEW

 

PROJECT UPDATE

Remediation of the Bloody Brook Voluntary Cleanup Site is complete.  The work began at the most upstream portion of the site (the wooded area near the NYS Thruway) in 2014 and was completed in spring 2017.  

During that time, approximately 39,000 tons of soil and sediment were removed from the brook channel, side banks and properties adjacent to the affected areas.

After completing the majority of remedial construction from 2014 to 2016, throughout the months of March through June 2017, Lockheed Martin’s remedial contractor (AECOM) cleaned up soil and restored an area outside of the brook at one property (an apartment complex) just off of Old Liverpool Road to complete the project.  

Below:  Portion of the 2017 apartment complex property after remediation and restoration (July 2017).Photo 1:  Portion of the 2017 apartment complex property after remediation and restoration (July 2017).

Below:  Looking downstream from the wooded area (summer 2017).

What’s Next for the Site

To complete the requirements of the March 2014 Decision Document, Lockheed Martin is compiling the Site Management Plan (SMP) and Final Engineering Report (FER). 

The SMP provides a general description of the site, notes the controls in-place and describes the nature and extent of the remaining contamination at the site.  As part of the SMP, Lockheed Martin will send notices annually to property owners within the site where residual cadmium remains below remedial excavation depths (that is, below 4 feet in residential areas). 

These notices will remind property owners of the potential presence of residual cadmium.  It will provide detailed information about where it could be encountered and what to do if the owner should need to dig within these areas.

The FER documents the complete remedial program implementation and is required to receive a certificate of completion or closure letter from the New York State Department of Environmental Conservation (NYSDEC).  Implementation of the SMP is the last phase of a remedial program, which begins with the closure letter. Site management ensures the safe (re)use of properties where contamination remains in place.

Lockheed Martin is now focusing on site monitoring, restoration and planning for the five year maintenance and monitoring period ahead.  Annual inspections will occur for five years following completion of restoration activities to ensure no erosion of the channel and banks is occurring and that the vegetation is growing as intended. 

These annual inspections will comply with the March 2014 Decision Document prepared by the NYSDEC, property-specific restoration agreements and the NYSDEC approved restoration work plans for the site.  As needed, based on these inspections, vegetation may need to be replaced and the brook side banks may require minor repairs.

Crayfish in the brook will also be sampled beginning in 2018, and again in 2020, to assess their cadmium concentrations following the completion of remedial activities. 

Results from samples collected before remediation will be used as a baseline for comparison of the cadmium concentrations.  This data will help determine the effectiveness of the site remediation in mitigating potential cadmium impacts to the brook.

Look for updated post-remediation information on this website for the next five years.

Below:  Ducks in brook near the wooded area (summer 2017).



GLOSSARY: View a list of terms commonly used in relation to general environmental remediation efforts that can be found throughout this Web site.

 

ACRONYMS: View a list of nicknames commonly used in relation to general environmental remediation efforts that can be found throughout this Web site.

 






HISTORICAL TIMELINE OF INVESTIGATON & CLEANUP

1947 - General Electric (a Lockheed Martin heritage company) opened its doors at Electronics Park.

1993 - The facility became part of Martin Marietta in 1993.

1995 - The facility became part of Lockheed Martin after Martin Marietta and Lockheed merged.

1996 - The New York State Department of Environmental Conservation (NYSDEC), during an environmental investigation of tributaries that flow into Onondaga Lake, detected elevated cadmium levels.  

1996 - Following NYSDEC testing, Lockheed Martin began voluntary environmental investigations.

1997 - Lockheed Martin removed 325 tons of sediment from a 750-foot stretch of the West Branch of the brook closest to the facility.

2001-2007 - Lockheed Martin collected more than 1,000 soil samples further downstream and found elevated levels of cadmium at depths ranging to 15 feet 

2002 - Lockheed Martin entered into a Voluntary Cleanup Agreement with NYSDEC.

2005 - Lockheed Martin created a Remedial Action Work Plan (RAWP) that it submitted to NYSDEC

2008 - Lockheed Martin removed sediment from four sets of culverts along the West Branch of Bloody Brook.

2009 - Lockheed Martin assisted with soil removal from properties included in an Onondaga County stormwater drainage improvement project.

2009 - Lockheed Martin submitted a revised RAWP  

2010-2011 - Lockheed Martin and NYSDEC determined that additional soil samples needed to be collected from properties  

2011 - Lockheed Martin submitted a sampling work plan to the NYSDEC which was approved

2013 - Lockheed Martin submitted a revised RAWP to NYSDEC which incorporated the results of the 2011 soil sampling.

2013 - Lockheed Martin collected additional soil samples from some residential properties.

2013 - NYSDEC completed its review of the 2013 revision to the RAWP, and based on its content, developed a Proposed Decision Document

2014 - Tree Removal Work Plan for  2015 Construction Season was released

2014  - NYSDEC issued a final Decision Document which included responses to public comments and the administrative record for the site.

2014 - Lockheed Martin began cleanup activities in the most upstream portion of the Bloody Brook remediation site (the wooded area near the NYS Thruway).  

2015 - Cleanup effort began in April in the wooded area where the 2014 activities left off, and continued downstream through the residential area up to the Floradale Road brook crossing. 

2015 - Construction & Restoration Work Plan was released

2016 - Remedial construction activities were completed for Bloody Brook and its side banks within the Onondaga County drainage district easement from the downstream side of Floradale Road to the site boundary at Onondaga Lake Parkway.

2016 - Construction & Restoration Work Plan was released

2016 - Tree Removal Work Plan & Waste Characterization Soil Sampling Plan was released

2017 – Lockheed Martin completed remediation of the Bloody Brook site with the cleanup and restoration of an apartment complex property adjacent to the brook.


If you have questions, please don’t hesitate to contact:

JILL FONTE,  PROJECT MANAGER JILL.A.FONTE@LMCO.COM